ITAC Assessment: WM0227
ITAC logo
ITAC Assessment: WM0227
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Cork
NAICS 339991: Gasket, Packing, and Sealing Device Manufacturing
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 125,000
ft2
Annual Production 18,000,000
lb
Production Hrs. Annual 3,120
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,400 1,072,215
kWh
Electricity Demand $74,330 4,693
kW-mo/yr
Electricity Fees $25,196 -
Natural Gas $39,744 6,541
MMBtu
Waste Disposal Costs
Water Usage $5,616 1,806
Tgal
TOTAL YEARLY COSTS $232,286
RECOMMENDED SAVINGS* $8,148 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,765 $7,055 $3,349
40,839
kWh
$1,416
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,869 $2,450 $1,478
18,023
kWh
$391
-
kW-mo/yr
03 2.4221: Install compressor air intakes in coolest locations $787 $2,103 $622
7,592
kWh
$165
-
kW-mo/yr
04 2.4239: Eliminate or reduce compressed air usage $727 - $575
7,009
kWh
$152
-
kW-mo/yr
TOTAL RECOMMENDED $8,148 $11,608 $6,024
73,463
kWh
$2,124
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs