| Assessment Year | 2024 |
|---|---|
| Principal Product | Cork |
| NAICS | 339991: Gasket, Packing, and Sealing Device Manufacturing |
| SIC | 3053: Gaskets, Packing, and Sealing Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
125,000
ft2
|
| Annual Production | 18,000,000
lb
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $87,400 | 1,072,215 |
kWh
|
$0.082 | |
| Electricity Demand | $74,330 | 4,693 |
kW-mo/yr
|
$15.84 | |
| Electricity Fees | $25,196 | - |
|
- | |
| Natural Gas | $39,744 | 6,541 |
MMBtu
|
$6.08 | |
| Waste Disposal Costs | |||||
| Water Usage | $5,616 | 1,806 |
Tgal
|
$3.11 | |
| TOTAL YEARLY COSTS | $232,286 | ||||
| RECOMMENDED SAVINGS* | $8,148 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $5,492 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,765 | $7,055 |
$3,349
40,839
kWh
|
$1,416
-
kW-mo/yr
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,869 | $2,450 |
$1,478
18,023
kWh
|
$391
-
kW-mo/yr
|
|
| 03 | 2.4221: Install compressor air intakes in coolest locations | $787 | $2,103 |
$622
7,592
kWh
|
$165
-
kW-mo/yr
|
|
| 04 | 2.4239: Eliminate or reduce compressed air usage | $727 | - |
$575
7,009
kWh
|
$152
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $8,148 | $11,608 |
$6,024
73,463
kWh
|
$2,124
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $5,492 | $7,055 |
$3,924
47,848
kWh
|
$1,568
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs