Assessment Year | 1998 |
---|---|
Principal Product | Copper Foil |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 175 |
Plant Area |
200,000
ft2
|
Annual Production | 17,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $4,184,363 | 137,016,415 |
kWh
|
$0.031 |
Electricity Demand | $1,700,273 | 212,216 |
kW-mo/yr
|
$8.01 |
Electricity Fees | $477,175 | - |
|
- |
Natural Gas | $90,238 | 19,141 |
MMBtu
|
$4.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,277,723 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $749,867 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $244,239 | $410,200 |
$244,239
8,160,317
kWh
|
- | - | - | - | - | - | - | - | |
02 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $955,252 | $4,000,000 |
$2,382,323
78,008,794
kWh
|
$961,439
-
kW-mo/yr
|
$271,675 |
$(-2,660,185.0)
-
MMBtu
|
- | - | - | - | - | |
03 | 2.2693: Use waste heat steam for absorption refrigeration | $395,073 | $1,524,052 |
$212,577
7,102,579
kWh
|
$182,496
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
04 | 2.2628: Utilize a less expensive cooling method | $17,372 | $80,000 |
$17,380
727,433
kWh
|
- | - | - | - | - | - | - |
$(-8.0)
-
Tgal
|
|
05 | 2.2612: Use cooling tower water instead of refrigeration | $69,699 | $225,000 |
$69,699
2,917,057
kWh
|
- | - | - | - | - | - | - | - | |
06 | 3.6192: Use a less expensive method of waste removal | $768 | $60 | - | - | - | - |
$768
-
lb
|
- | - | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $12,819 | $60 | - | - | - | - |
$16,419
-
lb
|
- | $(-3,600.0) | - | - | |
08 | 2.8113: Purchase gas directly from a contract gas supplier | $65,562 | $7,000 | - | - | - | - | - | - | $65,562 | - | - | |
09 | 2.8114: Change rate schedules or other changes in utility service | $498,755 | $240 | - | - | - | - | - | - | $498,755 | - | - | |
10 | 4.652: Replace existing equipment with more suitable substitutes | $6,873 | $3,125 | - | - | - | - | - | $(-150.0) | $7,570 | $(-525.0) |
$(-22.0)
-
Tgal
|
|
11 | 4.445: Install equipment to move product | $11,311 | $14,500 |
$232
7,620
kWh
|
$129
-
kW-mo/yr
|
- | - | - | $10,950 | - | - | - | |
TOTAL RECOMMENDED | $2,277,723 | $6,264,237 |
$2,926,450
96,923,800
kWh
|
$1,144,064
-
kW-mo/yr
|
$271,675 |
$(-2,660,185.0)
-
MMBtu
|
$17,187
-
lb
|
$10,800 | $568,287 | $(-525.0) |
$(-30.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $749,867 | $413,565 |
$244,239
8,160,317
kWh
|
- | - | - | - | $(-150.0) | $506,325 | $(-525.0) |
$(-22.0)
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs