ITAC Assessment: WM0218
ITAC logo
ITAC Assessment: WM0218
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product waste water
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $5
M
to 10
M
# of Employees 103
Plant Area 2,257,403
ft2
Annual Production 30,000,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,631,751 32,792,636
kWh
Electricity Demand $738,336 58,899
kW-mo/yr
Electricity Fees $166,982 -
Natural Gas $417,515 118,023
MMBtu
Waste Disposal Costs
Water Usage $49,833 12,944
Tgal
TOTAL YEARLY COSTS $3,004,417
RECOMMENDED SAVINGS* $57,918 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4314: Use synthetic lubricant $16,984 $11,275 $12,647
252,934
kWh
$4,337
-
kW-mo/yr
-
02 2.6218: Turn off equipment when not in use $12,515 - - - $12,515
-
MMBtu
03 2.7221: Lower temperature during the winter season and vice-versa $12,508 - - - $12,508
-
MMBtu
04 2.7135: Install occupancy sensors $11,685 $1,659 $9,241
184,826
kWh
$2,444
-
kW-mo/yr
-
05 2.4221: Install compressor air intakes in coolest locations $2,267 $2,345 $1,687
33,748
kWh
$579
-
kW-mo/yr
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,959 $3,900 $1,458
29,162
kWh
$501
-
kW-mo/yr
-
TOTAL RECOMMENDED $57,918 $19,179 $25,034
500,670
kWh
$7,861
-
kW-mo/yr
$25,023
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs