ITAC Assessment: UW0052
ITAC logo
ITAC Assessment: UW0052
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Steel Castings
NAICS 331513: Steel Foundries (except Investment)
SIC 3325: Steel Foundries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 80,000
ft2
Annual Production 2,500
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,092,524 22,576,056
kWh
Electricity Demand $540,281 94,290
kW-mo/yr
Natural Gas $1,241,831 139,620
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $102,531 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.2311: Heat treat parts only to required specifications or standards $43,653 - $39,200
800,000
kWh
- - $4,453
02 2.4133: Use most efficient type of electric motors $26,448 $326,103 $15,715
324,700
kWh
$10,733
-
kW-mo/yr
- -
03 2.6218: Turn off equipment when not in use $22,100 - - - $22,100
-
MMBtu
-
04 2.7231: Use radiant heater for spot heating $10,330 $10,000 - - $10,330
-
MMBtu
-
TOTAL RECOMMENDED $102,531 $336,103 $54,915
1,124,700
kWh
$10,733
-
kW-mo/yr
$32,430
-
MMBtu
$4,453
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs