| Assessment Year | 2011 |
|---|---|
| Principal Product | Steel Castings |
| NAICS | 331513: Steel Foundries (except Investment) |
| SIC | 3325: Steel Foundries, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
80,000
ft2
|
| Annual Production | 2,500
pieces
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,092,524 | 22,576,056 |
kWh
|
$0.048 |
| Electricity Demand | $540,281 | 94,290 |
kW-mo/yr
|
$5.73 |
| Natural Gas | $1,241,831 | 139,620 |
MMBtu
|
$8.89 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $102,531 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2311: Heat treat parts only to required specifications or standards | $43,653 | - |
$39,200
800,000
kWh
|
- | - | $4,453 | |
| 02 | 2.4133: Use most efficient type of electric motors | $26,448 | $326,103 |
$15,715
324,700
kWh
|
$10,733
-
kW-mo/yr
|
- | - | |
| 03 | 2.6218: Turn off equipment when not in use | $22,100 | - | - | - |
$22,100
-
MMBtu
|
- | |
| 04 | 2.7231: Use radiant heater for spot heating | $10,330 | $10,000 | - | - |
$10,330
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $102,531 | $336,103 |
$54,915
1,124,700
kWh
|
$10,733
-
kW-mo/yr
|
$32,430
-
MMBtu
|
$4,453 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs