Assessment Year | 2024 |
---|---|
Principal Product | Electrical Terminal Blocks and Connectors |
NAICS | 334417: Electronic Connector Manufacturing |
SIC | 3613: Switchgear and Switchboard Apparatus |
Sales Range | $100 M to 500M |
# of Employees | 150 |
Plant Area |
114,000
ft2
|
Annual Production | 2,400,000
units
|
Production Hrs. Annual | 2,160
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $53,864 | 899,314 |
kWh
|
$0.060 | |
Electricity Demand | $33,930 | 2,235 |
kW-mo/yr
|
$15.18 | |
Electricity Fees | $20,992 | - |
|
- | |
Natural Gas | $55,685 | 6,187 |
MMBtu
|
$9.00 | |
Waste Disposal Costs | |||||
Water Usage | $5,550 | 566 |
Tgal
|
$9.81 | |
TOTAL YEARLY COSTS | $170,021 | ||||
RECOMMENDED SAVINGS* | $18,723 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $13,096 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4112: Install soft-start to eliminate nuisance trips | $7,114 | $700 | - |
$7,114
-
kW-mo/yr
|
- | |
02 | 2.7231: Use radiant heater for spot heating | $5,517 | $16,193 | - | - |
$5,517
-
MMBtu
|
|
03 | 2.2414: Use waste heat from hot flue gases to preheat | $4,617 | $9,500 | - | - |
$4,617
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,148 | $150 |
$852
14,204
kWh
|
$296
-
kW-mo/yr
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $216 | $345 |
$160
2,665
kWh
|
$56
-
kW-mo/yr
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $110 | - |
$87
1,449
kWh
|
$23
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $18,723 | $26,888 |
$1,099
18,318
kWh
|
$7,490
-
kW-mo/yr
|
$10,134
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,096 | $10,695 |
$1,012
16,869
kWh
|
$7,466
-
kW-mo/yr
|
$4,617
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs