ITAC Assessment: WM0211
ITAC logo
ITAC Assessment: WM0211
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Electrical Terminal Blocks and Connectors
NAICS 334417: Electronic Connector Manufacturing
SIC 3613: Switchgear and Switchboard Apparatus
Sales Range $100
M
to 500
M
# of Employees 150
Plant Area 114,000
ft2
Annual Production 2,400,000
units
Production Hrs. Annual 2,160
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,864 899,314
kWh
Electricity Demand $33,930 2,235
kW-mo/yr
Electricity Fees $20,992 -
Natural Gas $55,685 6,187
MMBtu
Waste Disposal Costs
Water Usage $5,550 566
Tgal
TOTAL YEARLY COSTS $170,021
RECOMMENDED SAVINGS* $18,723 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,096

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4112: Install soft-start to eliminate nuisance trips $7,114 $700 - $7,114
-
kW-mo/yr
-
02 2.7231: Use radiant heater for spot heating $5,517 $16,193 - - $5,517
-
MMBtu
03 2.2414: Use waste heat from hot flue gases to preheat $4,617 $9,500 - - $4,617
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,148 $150 $852
14,204
kWh
$296
-
kW-mo/yr
-
05 2.4221: Install compressor air intakes in coolest locations $216 $345 $160
2,665
kWh
$56
-
kW-mo/yr
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $110 - $87
1,449
kWh
$23
-
kW-mo/yr
-
TOTAL RECOMMENDED $18,723 $26,888 $1,099
18,318
kWh
$7,490
-
kW-mo/yr
$10,134
-
MMBtu
TOTAL IMPLEMENTED $13,096 $10,695 $1,012
16,869
kWh
$7,466
-
kW-mo/yr
$4,617
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs