| Assessment Year | 2023 |
|---|---|
| Principal Product | Medical devices |
| NAICS | 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing |
| SIC | 3679: Electronic Components, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 800 |
| Plant Area |
141,000
ft2
|
| Annual Production | 2,000
units
|
| Production Hrs. Annual | 6,552
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $208,901 | 4,225,355 |
kWh
|
$0.049 | |
| Electricity Demand | $77,649 | 9,216 |
kW-mo/yr
|
$8.43 | |
| Electricity Fees | $(-22,772.0) | - |
|
- | |
| Natural Gas | $95,233 | 15,322 |
MMBtu
|
$6.22 | |
| Waste Disposal Costs | |||||
| Water Usage | $35,924 | 4,435 |
Tgal
|
$8.10 | |
| Water Disposal | $19,958 | 4,435 |
Tgal
|
$4.50 | |
| TOTAL YEARLY COSTS | $414,893 | ||||
| RECOMMENDED SAVINGS* | $29,253 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $15,913 | $15,200 | - | - |
$15,913
-
MMBtu
|
- | |
| 02 | 3.4116: Meter recycled water (to reduce sewer charges) | $7,589 | $2,500 | - | - | - |
$7,589
-
Tgal
|
|
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $3,633 | $7,520 | - | - |
$3,633
-
MMBtu
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,077 | $1,814 |
$819
16,710
kWh
|
$258
-
kW-mo/yr
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $1,042 | $195 |
$838
17,108
kWh
|
$203
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $29,253 | $27,229 |
$1,657
33,818
kWh
|
$461
-
kW-mo/yr
|
$19,546
-
MMBtu
|
$7,589
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs