ITAC Assessment: WM0190
ITAC logo
ITAC Assessment: WM0190
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Wastewater Treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 26
Plant Area 466,092
ft2
Annual Production 1,092,000
Tgal
Production Hrs. Annual 8,736
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,179 1,511,749
kWh
Electricity Demand $34,206 2,980
kW-mo/yr
Electricity Fees $19,374 -
Natural Gas $67,402 8,896
MMBtu
TOTAL YEARLY COSTS $189,161
RECOMMENDED SAVINGS* $14,317 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,304

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4314: Use synthetic lubricant $7,127 $11,275 $5,279
117,307
kWh
$1,848
-
kW-mo/yr
-
02 2.7444: Close holes and openings in building such as broken windows $3,068 $525 - - $3,068
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,889 $5,872 $232
5,165
kWh
$1,656
-
kW-mo/yr
-
04 2.7444: Close holes and openings in building such as broken windows $1,598 $456 - - $1,598
-
MMBtu
05 2.7135: Install occupancy sensors $400 $843 $127
2,817
kWh
$273
-
kW-mo/yr
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $236 $1,000 $186
4,129
kWh
$50
-
kW-mo/yr
-
TOTAL RECOMMENDED $14,317 $19,971 $5,824
129,418
kWh
$3,828
-
kW-mo/yr
$4,666
-
MMBtu
TOTAL IMPLEMENTED $3,304 $1,525 $186
4,129
kWh
$50
-
kW-mo/yr
$3,068
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs