| Assessment Year | 2022 |
|---|---|
| Principal Product | Label convereting and printing |
| NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
| SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 500 |
| Plant Area |
275,000
ft2
|
| Annual Production | 5,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $327,430 | 5,284,531 |
kWh
|
$0.062 |
| Electricity Demand | $204,343 | 13,458 |
kW-mo/yr
|
$15.18 |
| Electricity Fees | $0.1 | - |
|
- |
| Natural Gas | $52,914 | 14,162 |
MMBtu
|
$3.74 |
| TOTAL YEARLY COSTS | $584,687 | |||
| RECOMMENDED SAVINGS* | $12,550 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,646 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,582 | $3,000 |
$2,694
43,474
kWh
|
$888
-
kW-mo/yr
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,815 | $1,500 |
$1,233
19,904
kWh
|
$581
-
kW-mo/yr
|
- | |
| 03 | 2.2437: Recover waste heat from equipment | $1,771 | $1,090 | - | - |
$1,771
-
MMBtu
|
|
| 04 | 2.7221: Lower temperature during the winter season and vice-versa | $1,638 | - | - | - |
$1,638
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,567 | $844 |
$1,150
18,564
kWh
|
$417
-
kW-mo/yr
|
- | |
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $1,495 | $5,000 | - | - |
$1,495
-
MMBtu
|
|
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $682 | $2,268 |
$513
8,281
kWh
|
$169
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $12,550 | $13,702 |
$5,590
90,223
kWh
|
$2,056
-
kW-mo/yr
|
$4,904
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $7,646 | $7,612 |
$5,590
90,223
kWh
|
$2,056
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs