ITAC Assessment: WM0171
ITAC logo
ITAC Assessment: WM0171
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Label convereting and printing
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 500
Plant Area 275,000
ft2
Annual Production 5,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $327,430 5,284,531
kWh
Electricity Demand $204,343 13,458
kW-mo/yr
Electricity Fees $0.1 -
Natural Gas $52,914 14,162
MMBtu
TOTAL YEARLY COSTS $584,687
RECOMMENDED SAVINGS* $12,550 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,646

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,582 $3,000 $2,694
43,474
kWh
$888
-
kW-mo/yr
-
02 2.4221: Install compressor air intakes in coolest locations $1,815 $1,500 $1,233
19,904
kWh
$581
-
kW-mo/yr
-
03 2.2437: Recover waste heat from equipment $1,771 $1,090 - - $1,771
-
MMBtu
04 2.7221: Lower temperature during the winter season and vice-versa $1,638 - - - $1,638
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,567 $844 $1,150
18,564
kWh
$417
-
kW-mo/yr
-
06 2.2414: Use waste heat from hot flue gases to preheat $1,495 $5,000 - - $1,495
-
MMBtu
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $682 $2,268 $513
8,281
kWh
$169
-
kW-mo/yr
-
TOTAL RECOMMENDED $12,550 $13,702 $5,590
90,223
kWh
$2,056
-
kW-mo/yr
$4,904
-
MMBtu
TOTAL IMPLEMENTED $7,646 $7,612 $5,590
90,223
kWh
$2,056
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs