Assessment Year | 2019 |
---|---|
Principal Product | Machined Parts |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 146 |
Plant Area |
125,000
ft2
|
Annual Production | 4,523,000
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $166,366 | 2,471,224 |
kWh
|
$0.067 | |
Electricity Demand | $92,316 | 6,829 |
kW-mo/yr
|
$13.52 | |
Electricity Fees | $13,846 | - |
|
- | |
Natural Gas | $49,332 | 8,222 |
MMBtu
|
$6.00 | |
Waste Disposal Costs | |||||
Water Usage | $7,727 | 963 |
Tgal
|
$8.02 | |
TOTAL YEARLY COSTS | $329,587 | ||||
RECOMMENDED SAVINGS* | $50,688 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $14,340 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,440 | $50,620 |
$10,261
152,424
kWh
|
$6,179
-
kW-mo/yr
|
- | - | |
02 | 2.3212: Optimize plant power factor | $12,647 | $110,950 | - | - | $12,647 | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $7,779 | $16,000 | - | - | - |
$7,779
-
MMBtu
|
|
04 | 2.7444: Close holes and openings in building such as broken windows | $6,618 | $6,180 | - | - | - |
$6,618
-
MMBtu
|
|
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,759 | $10,600 |
$3,759
55,839
kWh
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,752 | $7,100 |
$1,752
26,026
kWh
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,693 | $4,000 |
$1,277
18,972
kWh
|
$416
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $50,688 | $205,450 |
$17,049
253,261
kWh
|
$6,595
-
kW-mo/yr
|
$12,647 |
$14,397
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,340 | $114,950 |
$1,277
18,972
kWh
|
$416
-
kW-mo/yr
|
$12,647 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs