| Assessment Year | 2000 |
|---|---|
| Principal Product | Lawnmowers |
| NAICS |
n/a
|
| SIC | 3524: Lawn and Garden Tractors and Home Lawn and Garden Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 697 |
| Plant Area |
375,491
ft2
|
| Annual Production | 2,135,088
pieces
|
| Production Hrs. Annual | 5,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $349,006 | 13,580,891 |
kWh
|
$0.026 |
| Electricity Demand | $274,482 | 23,124 |
kW-mo/yr
|
$11.87 |
| Electricity Fees | $49,880 | - |
|
- |
| Natural Gas | $113,058 | 45,220 |
MMBtu
|
$2.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $264,258 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $126,943 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,919 | $1,150 |
$5,584
146,835
kWh
|
- | $335 | - | - | - | - | - | |
| 02 | 2.1231: Establish burner maintenance schedule for boilers | $870 | - | - | - | - |
$1,320
-
MMBtu
|
- | $(-450.0) | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,412 | $16,800 |
$5,106
134,525
kWh
|
- | $306 | - | - | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,002 | $11,083 |
$1,889
49,824
kWh
|
- | $113 | - | - | - | - | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $20,316 | $3,940 |
$9,258
419,109
kWh
|
$9,908
-
kW-mo/yr
|
$1,150 | - | - | - | - | - | |
| 06 | 2.7224: Reduce space conditioning during non-working hours | $4,224 | $8,700 |
$3,985
104,924
kWh
|
- | $239 | - | - | - | - | - | |
| 07 | 4.625: Develop standard operating procedures | $88,200 | $34,000 | - | - | - | - | - | - | - | $88,200 | |
| 08 | 2.2514: Cover open tanks | $6,100 | $5,390 | - | - | - |
$6,100
-
MMBtu
|
- | - | - | - | |
| 09 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $2,967 | $9,200 |
$1,082
26,964
kWh
|
- | - |
$1,885
-
MMBtu
|
- | - | - | - | |
| 10 | 3.1162: Use less wasteful packaging | $5,073 | $3,500 | - | - | - | - | - | $3,453 | $1,620 | - | |
| 11 | 3.3122: Use filtration, centrifuging to remove contaminants | $123,175 | $50,000 | - | - | - | - |
$118,765
-
gal
|
$4,410 | - | - | |
| TOTAL RECOMMENDED | $264,258 | $143,763 |
$26,904
882,181
kWh
|
$9,908
-
kW-mo/yr
|
$2,143 |
$9,305
-
MMBtu
|
$118,765
-
gal
|
$7,413 | $1,620 | $88,200 | ||
| TOTAL IMPLEMENTED | $126,943 | $75,673 |
$25,822
855,217
kWh
|
$9,908
-
kW-mo/yr
|
$2,143 |
$1,320
-
MMBtu
|
- | $(-450.0) | - | $88,200 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs