Assessment Year | 2019 |
---|---|
Principal Product | Forged Steel Components |
NAICS | 332111: Iron and Steel Forging |
SIC | 3462: Iron and Steel Forgings |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
155,000
ft2
|
Annual Production | 6,000
ton
|
Production Hrs. Annual | 3,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $161,502 | 2,592,728 |
kWh
|
$0.062 | |
Electricity Demand | $127,060 | 9,398 |
kW-mo/yr
|
$13.52 | |
Electricity Fees | $21,387 | - |
|
- | |
Natural Gas | $914,714 | 236,094 |
MMBtu
|
$3.87 | |
Waste Disposal Costs | |||||
Water Usage | $117,163 | 20,142 |
Tgal
|
$5.82 | |
TOTAL YEARLY COSTS | $1,341,826 | ||||
RECOMMENDED SAVINGS* | $150,224 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $64,213 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $59,838 | $46,000 | - | - |
$59,838
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $44,870 | $52,117 |
$23,902
383,702
kWh
|
$20,968
-
kW-mo/yr
|
- | |
03 | 2.2113: Repair or replace steam traps | $8,847 | $16,800 | - | - |
$8,847
-
MMBtu
|
|
04 | 2.4314: Use synthetic lubricant | $7,620 | $25,000 |
$4,078
65,461
kWh
|
$3,542
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,539 | $3,900 |
$6,728
108,000
kWh
|
$811
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,828 | $7,410 |
$1,765
28,325
kWh
|
$3,063
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,712 | $8,360 |
$3,712
59,587
kWh
|
- | - | |
08 | 2.6218: Turn off equipment when not in use | $2,876 | - |
$2,876
48,000
kWh
|
- | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,813 | $3,700 |
$1,506
24,170
kWh
|
$1,307
-
kW-mo/yr
|
- | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,580 | $950 |
$1,381
22,170
kWh
|
$1,199
-
kW-mo/yr
|
- | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,463 | $880 |
$917
14,711
kWh
|
$546
-
kW-mo/yr
|
- | |
12 | 2.4221: Install compressor air intakes in coolest locations | $1,255 | $1,513 |
$606
9,666
kWh
|
$649
-
kW-mo/yr
|
- | |
13 | 2.7134: Use photocell controls | $1,013 | $290 |
$1,013
16,255
kWh
|
- | - | |
14 | 2.7135: Install occupancy sensors | $970 | $800 |
$970
15,573
kWh
|
- | - | |
TOTAL RECOMMENDED | $150,224 | $167,720 |
$49,453
795,620
kWh
|
$32,086
-
kW-mo/yr
|
$68,685
-
MMBtu
|
||
TOTAL IMPLEMENTED | $64,213 | $93,917 |
$30,856
497,163
kWh
|
$24,510
-
kW-mo/yr
|
$8,847
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs