Assessment Year | 2018 |
---|---|
Principal Product | Soy Sauce |
NAICS | 311991: Perishable Prepared Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 200 |
Plant Area |
700,000
ft2
|
Annual Production | 30,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,586,162 | 32,636,800 |
kWh
|
$0.049 | |
Electricity Demand | $872,950 | 63,719 |
kW-mo/yr
|
$13.70 | |
Electricity Fees | $92,087 | - |
|
- | |
Natural Gas | $1,217,376 | 310,521 |
MMBtu
|
$3.92 | |
Waste Disposal Costs | |||||
Water Usage | $363,154 | 39,162 |
Tgal
|
$9.27 | |
TOTAL YEARLY COSTS | $4,131,729 | ||||
RECOMMENDED SAVINGS* | $176,465 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $15,165 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $95,648 | $66,000 | - | - |
$95,648
-
MMBtu
|
|
02 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $26,985 | $20,000 | - | - |
$26,985
-
MMBtu
|
|
03 | 2.9114: Use solar heat to make electricty | $14,198 | $48,500 |
$14,198
276,867
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $10,475 | $8,650 |
$7,557
155,495
kWh
|
$2,918
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,011 | $15,236 |
$5,779
118,908
kWh
|
$2,232
-
kW-mo/yr
|
- | |
06 | 2.2113: Repair or replace steam traps | $7,154 | $6,480 | - | - |
$7,154
-
MMBtu
|
|
07 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $7,029 | $1,710 | - | - |
$7,029
-
MMBtu
|
|
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,101 | $2,850 |
$2,958
60,873
kWh
|
$1,143
-
kW-mo/yr
|
- | |
09 | 2.7221: Lower temperature during the winter season and vice-versa | $2,864 | - |
$778
15,996
kWh
|
$2,087
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $176,465 | $169,426 |
$31,270
628,139
kWh
|
$8,379
-
kW-mo/yr
|
$136,816
-
MMBtu
|
||
TOTAL IMPLEMENTED | $15,165 | $21,716 |
$5,779
118,908
kWh
|
$2,232
-
kW-mo/yr
|
$7,154
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs