Assessment Year | 2018 |
---|---|
Principal Product | Waste Water Treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 95 |
Plant Area |
2,257,403
ft2
|
Annual Production | 11,680,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,498,531 | 34,438,545 |
kWh
|
$0.044 | |
Electricity Demand | $558,896 | 53,509 |
kW-mo/yr
|
$10.44 | |
Electricity Fees | $250,906 | - |
|
- | |
Natural Gas | $881,221 | 213,082 |
MMBtu
|
$4.14 | |
Waste Disposal Costs | |||||
Water Usage | $47,368 | 15,975 |
Tgal
|
$2.97 | |
TOTAL YEARLY COSTS | $3,236,922 | ||||
RECOMMENDED SAVINGS* | $137,310 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $54,971 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $60,763 | $200,000 |
$45,726
1,050,925
kWh
|
$15,037
-
kW-mo/yr
|
- | - | - | |
02 | 2.4314: Use synthetic lubricant | $28,087 | $20,000 |
$21,136
485,780
kWh
|
$6,951
-
kW-mo/yr
|
- | - | - | |
03 | 2.9114: Use solar heat to make electricty | $11,320 | $99,200 |
$11,320
260,185
kWh
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,991 | $13,400 |
$8,271
190,092
kWh
|
$2,720
-
kW-mo/yr
|
- | - | - | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $9,439 | - | - | - | - |
$9,439
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,920 | $7,291 |
$6,580
151,239
kWh
|
$2,340
-
kW-mo/yr
|
- | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,638 | $1,400 |
$1,990
45,745
kWh
|
$648
-
kW-mo/yr
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,196 | $2,270 |
$1,057
24,283
kWh
|
$348
-
kW-mo/yr
|
- | - | $791 | |
09 | 2.7135: Install occupancy sensors | $1,932 | $1,308 |
$1,305
30,000
kWh
|
$627
-
kW-mo/yr
|
- | - | - | |
10 | 2.7144: Install spectral reflectors / delamp | $358 | - |
$182
4,200
kWh
|
$176
-
kW-mo/yr
|
- | - | - | |
11 | 2.6218: Turn off equipment when not in use | $350 | - |
$267
6,132
kWh
|
$83
-
kW-mo/yr
|
- | - | - | |
12 | 2.3132: Recharge batteries on during off-peak demand periods | $207 | - | - | - | $207 | - | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $109 | $98 |
$109
2,497
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $137,310 | $344,967 |
$97,943
2,251,078
kWh
|
$28,930
-
kW-mo/yr
|
$207 |
$9,439
-
MMBtu
|
$791 | ||
TOTAL IMPLEMENTED | $54,971 | $45,669 |
$40,339
927,139
kWh
|
$13,634
-
kW-mo/yr
|
$207 | - | $791 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs