Assessment Year | 2017 |
---|---|
Principal Product | Treat Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $1 M to 5M |
# of Employees | 5 |
Plant Area |
273,000
ft2
|
Annual Production | 80,001
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $94,095 | 1,854,454 |
kWh
|
$0.051 | |
Electricity Demand | $44,887 | 4,240 |
kW-mo/yr
|
$10.59 | |
Electricity Fees | $25,958 | - |
|
- | |
Natural Gas | $16,710 | 3,153 |
MMBtu
|
$5.30 | |
Waste Disposal Costs | |||||
Water Usage | $1,931 | 94 |
Tgal
|
$20.54 | |
Solid Waste (haz) | $150,000 | 1,414,000 |
lb
|
$0.11 | |
TOTAL YEARLY COSTS | $333,581 | ||||
RECOMMENDED SAVINGS* | $334,604 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,914 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.5311: Recover and reuse waste material | $282,127 | $836,828 | - | - | - |
$150,000
-
lb
|
- | $132,127 | |
02 | 2.9114: Use solar heat to make electricty | $27,888 | $228,151 |
$27,888
452,000
kWh
|
- | - | - | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,544 | $42,400 |
$11,315
223,001
kWh
|
$3,229
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7231: Use radiant heater for spot heating | $3,705 | $6,960 | - | - |
$3,705
-
MMBtu
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,624 | $1,590 |
$874
17,231
kWh
|
$750
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,520 | - |
$967
19,060
kWh
|
$553
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,182 | $1,400 |
$1,182
21,362
kWh
|
- | - | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $817 | $1,224 |
$635
12,520
kWh
|
$182
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.7224: Reduce space conditioning during non-working hours | $803 | - |
$72
1,413
kWh
|
- |
$731
-
MMBtu
|
- | - | - | |
10 | 3.4116: Meter recycled water (to reduce sewer charges) | $394 | - | - | - | - | - | $394 | - | |
TOTAL RECOMMENDED | $334,604 | $1,118,553 |
$42,933
746,587
kWh
|
$4,713
-
kW-mo/yr
|
$4,436
-
MMBtu
|
$150,000
-
lb
|
$394 | $132,127 | ||
TOTAL IMPLEMENTED | $1,914 | - |
$967
19,060
kWh
|
$553
-
kW-mo/yr
|
- | - | $394 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs