| Assessment Year | 2006 |
|---|---|
| Principal Product | bridges |
| NAICS | 333924: Industrial Truck, Tractor, Trailer, and Stacker Machinery Manufacturing |
| SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
350,000
ft2
|
| Annual Production | 200
pieces
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $102,927 | 4,161,600 |
kWh
|
$0.025 |
| Electricity Demand | $109,415 | 13,139 |
kW-mo/yr
|
$8.33 |
| Natural Gas | $360,176 | 39,969 |
MMBtu
|
$9.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $358,770 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $19,040 | $10,000 | - |
$19,040
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4224: Upgrade controls on compressors | $2,420 | $2,000 |
$790
32,215
kWh
|
- | - | - | $1,630 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,540 | $3,530 |
$10,110
411,510
kWh
|
$5,430
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.2314: Replace heat treating oven with more efficient unit | $104,490 | $16,800 | - | - | - |
$104,490
-
MMBtu
|
- | |
| 05 | 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat | $198,120 | $1,974,210 |
$125,000
4,161,600
kWh
|
$125,000
-
kW-mo/yr
|
$6,586 |
$(-58,466.0)
-
MMBtu
|
- | |
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $15,650 | $28,400 |
$(-620.0)
(-25,380)
kWh
|
$(-530.0)
-
kW-mo/yr
|
- |
$16,800
-
MMBtu
|
- | |
| 07 | 2.3212: Optimize plant power factor | $3,510 | $8,490 | - |
$3,510
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $358,770 | $2,043,430 |
$135,280
4,579,945
kWh
|
$152,450
-
kW-mo/yr
|
$6,586 |
$62,824
-
MMBtu
|
$1,630 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs