Assessment Year | 2016 |
---|---|
Principal Product | Cheese products |
NAICS | 311513: Cheese Manufacturing |
SIC | 2022: Natural, Processed, and Imitation Cheese |
Sales Range | $50 M to 100M |
# of Employees | 53 |
Plant Area |
37,315
ft2
|
Annual Production | 17,000
ton
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $324,779 | 6,862,259 |
kWh
|
$0.047 | |
Electricity Demand | $143,650 | 13,820 |
kW-mo/yr
|
$10.39 | |
Electricity Fees | $28,540 | - |
|
- | |
Natural Gas | $198,064 | 44,426 |
MMBtu
|
$4.46 | |
Waste Disposal Costs | |||||
Water Usage | $10,712 | 54,750 |
Tgal
|
$0.20 | |
Water Disposal | $275,349 | 54,000 |
Tgal
|
$5.10 | |
Solid Waste (non-haz) | $9,613 | 74,800 |
lb
|
$0.13 | |
TOTAL YEARLY COSTS | $990,707 | ||||
RECOMMENDED SAVINGS* | $28,398 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $26,063 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,839 | $5,000 |
$16,775
354,655
kWh
|
$5,064
-
kW-mo/yr
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,120 | $1,420 |
$2,397
50,668
kWh
|
$723
-
kW-mo/yr
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,511 | $3,000 |
$1,161
24,538
kWh
|
$350
-
kW-mo/yr
|
|
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,104 | $375 |
$848
17,932
kWh
|
$256
-
kW-mo/yr
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $824 | $2,005 |
$824
17,438
kWh
|
- | |
TOTAL RECOMMENDED | $28,398 | $11,800 |
$22,005
465,231
kWh
|
$6,393
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $26,063 | $6,795 |
$20,020
423,255
kWh
|
$6,043
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs