ITAC Assessment: WM0092
ITAC logo
ITAC Assessment: WM0092
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Cheese products
NAICS 311513: Cheese Manufacturing
SIC 2022: Natural, Processed, and Imitation Cheese
Sales Range $50
M
to 100
M
# of Employees 53
Plant Area 37,315
ft2
Annual Production 17,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $324,779 6,862,259
kWh
Electricity Demand $143,650 13,820
kW-mo/yr
Electricity Fees $28,540 -
Natural Gas $198,064 44,426
MMBtu
Waste Disposal Costs
Water Usage $10,712 54,750
Tgal
Water Disposal $275,349 54,000
Tgal
Solid Waste (non-haz) $9,613 74,800
lb
TOTAL YEARLY COSTS $990,707
RECOMMENDED SAVINGS* $28,398 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,063

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $21,839 $5,000 $16,775
354,655
kWh
$5,064
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,120 $1,420 $2,397
50,668
kWh
$723
-
kW-mo/yr
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,511 $3,000 $1,161
24,538
kWh
$350
-
kW-mo/yr
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,104 $375 $848
17,932
kWh
$256
-
kW-mo/yr
05 2.7142: Utilize higher efficiency lamps and/or ballasts $824 $2,005 $824
17,438
kWh
-
TOTAL RECOMMENDED $28,398 $11,800 $22,005
465,231
kWh
$6,393
-
kW-mo/yr
TOTAL IMPLEMENTED $26,063 $6,795 $20,020
423,255
kWh
$6,043
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs