Assessment Year | 2000 |
---|---|
Principal Product | Chemicals |
NAICS |
n/a
|
SIC | 2800: |
Sales Range | $100 M to 500M |
# of Employees | 210 |
Plant Area |
140,000
ft2
|
Annual Production | 80,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $553,250 | 20,274,912 |
kWh
|
$0.027 |
Electricity Demand | $531,219 | 30,828 |
kW-mo/yr
|
$17.23 |
Electricity Fees | $(-46,508.0) | - |
|
- |
Natural Gas | $3,321,518 | 1,039,849 |
MMBtu
|
$3.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $734,468 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $205,998 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $67,296 | $2,200 | - | - |
$67,296
-
MMBtu
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $6,190 | $1,400 |
$3,331
123,388
kWh
|
$2,859
-
kW-mo/yr
|
- | - | |
03 | 2.2121: Increase amount of condensate returned | $138,702 | $86,970 | - | - |
$138,702
-
MMBtu
|
- | |
04 | 2.1241: Reduce excessive boiler blowdown | $11,891 | $9,860 | - | - |
$11,891
-
MMBtu
|
- | |
05 | 2.4131: Size electric motors for peak operating efficiency | $106,009 | $100,000 |
$56,800
2,048,359
kWh
|
$49,209
-
kW-mo/yr
|
- | - | |
06 | 2.5123: Reduce fluid flow rates | $40,377 | $1,000 |
$25,490
618,113
kWh
|
$14,887
-
kW-mo/yr
|
- | - | |
07 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $364,003 | $3,000,000 |
$483,552
17,524,912
kWh
|
$405,600
-
kW-mo/yr
|
$(-262,349.0)
-
MMBtu
|
$(-262,800.0) | |
TOTAL RECOMMENDED | $734,468 | $3,201,430 |
$569,173
20,314,772
kWh
|
$472,555
-
kW-mo/yr
|
$(-44,460.0)
-
MMBtu
|
$(-262,800.0) | ||
TOTAL IMPLEMENTED | $205,998 | $89,170 | - | - |
$205,998
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs