| Assessment Year | 2018 |
|---|---|
| Principal Product | Rubber Products |
| NAICS | 326291: Rubber Product Manufacturing for Mechanical Use |
| SIC | 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods |
| Sales Range | $10 M to 50M |
| # of Employees | 340 |
| Plant Area |
200,000
ft2
|
| Annual Production | 14,000,000
lb
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,246,871 | 17,286,000 |
kWh
|
$0.072 |
| Electricity Demand | $260,755 | 37,364 |
kW-mo/yr
|
$6.98 |
| Electricity Fees | $72,514 | - |
|
- |
| Natural Gas | $355,214 | 62,339 |
MMBtu
|
$5.70 |
| TOTAL YEARLY COSTS | $1,935,354 | |||
| RECOMMENDED SAVINGS* | $141,637 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $109,027 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6212: Turn off equipment during breaks, reduce operating time | $31,439 | $2 |
$31,439
435,864
kWh
|
- | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,249 | $7 |
$3,634
50,380
kWh
|
$615
-
kW-mo/yr
|
- | - | |
| 03 | 2.4323: Use optimum size and capacity equipment | $831 | - |
$711
9,867
kWh
|
$120
-
kW-mo/yr
|
- | - | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $12,491 | $1,482 |
$12,491
173,179
kWh
|
- | - | - | |
| 05 | 2.7221: Lower temperature during the winter season and vice-versa | $5,641 | $800 | - | - | - |
$5,641
-
MMBtu
|
|
| 06 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $27,530 | $11,407 | - | - | - |
$27,530
-
MMBtu
|
|
| 07 | 2.7135: Install occupancy sensors | $323 | $87 |
$323
4,480
kWh
|
- | - | - | |
| 08 | 2.3212: Optimize plant power factor | $59,133 | $75,790 | - | - | $59,133 | - | |
| TOTAL RECOMMENDED | $141,637 | $89,575 |
$48,598
673,770
kWh
|
$735
-
kW-mo/yr
|
$59,133 |
$33,171
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $109,027 | $78,161 |
$44,253
613,523
kWh
|
- | $59,133 |
$5,641
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs