ITAC Assessment: WM0089
ITAC logo
ITAC Assessment: WM0089
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Spreadable Cheese
NAICS 311513: Cheese Manufacturing
SIC 2022: Natural, Processed, and Imitation Cheese
Sales Range $10
M
to 50
M
# of Employees 139
Plant Area 144,000
ft2
Annual Production 8,160
ton
Production Hrs. Annual 7,224
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $195,088 3,490,913
kWh
Electricity Demand $69,859 8,261
kW-mo/yr
Electricity Fees $8,604 -
Natural Gas $75,411 29,038
MMBtu
Waste Disposal Costs
Water Usage $71,903 11,020
Tgal
TOTAL YEARLY COSTS $420,865
RECOMMENDED SAVINGS* $84,156 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.7135: Install occupancy sensors $15,954 $6,213 $8,681
155,345
kWh
$7,273
-
kW-mo/yr
-
02 2.7134: Use photocell controls $628 $290 $357
6,372
kWh
$271
-
kW-mo/yr
-
03 3.2176: Increase use of automation $52,696 $6,000 - - $52,696
04 2.4231: Reduce the pressure of compressed air to the minimum required $3,394 - $2,794
49,998
kWh
$600
-
kW-mo/yr
-
05 2.2621: Modify refrigeration system to operate at a lower pressure $11,093 - $9,123
163,273
kWh
$1,970
-
kW-mo/yr
-
06 2.6211: Conserve energy by efficient use of vending machines $392 $690 $324
5,803
kWh
$68
-
kW-mo/yr
-
TOTAL RECOMMENDED $84,156 $13,193 $21,279
380,791
kWh
$10,182
-
kW-mo/yr
$52,696
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs