ITAC Assessment: WM0088
ITAC logo
ITAC Assessment: WM0088
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Single use plastic food lids, containers
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 87,500
ft2
Annual Production 6,000,000
units
Production Hrs. Annual 5,800
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $334,105 8,121,919
kWh
Electricity Demand $337,478 19,776
kW-mo/yr
Electricity Fees $251,816 -
Natural Gas $11,749 1,651
MMBtu
Waste Disposal Costs
Water Usage $22,174 2,368,168
Tgal
TOTAL YEARLY COSTS $957,322
RECOMMENDED SAVINGS* $173,709 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,245

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $71,275 $132,797 - $35,938
-
kW-mo/yr
$35,337 - -
02 2.2437: Recover waste heat from equipment $75,376 $50,000 $40,615
984,608
kWh
$34,761
-
kW-mo/yr
- - -
03 2.2437: Recover waste heat from equipment $9,940 $28,000 - - - $9,940
-
MMBtu
-
04 2.4221: Install compressor air intakes in coolest locations $8,075 $501 $4,815
116,800
kWh
$3,260
-
kW-mo/yr
- - -
05 3.4155: Meter waste water $4,267 $375 - - - - $4,267
06 2.7221: Lower temperature during the winter season and vice-versa $3,245 - - - - $3,245
-
MMBtu
-
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,531 $6,000 $848
20,545
kWh
$683
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $173,709 $217,673 $46,278
1,121,953
kWh
$74,642
-
kW-mo/yr
$35,337 $13,185
-
MMBtu
$4,267
TOTAL IMPLEMENTED $3,245 - - - - $3,245
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs