| Assessment Year | 2016 |
|---|---|
| Principal Product | Investment casting |
| NAICS | 331512: Steel Investment Foundries |
| SIC | 3324: Steel Investment Foundries |
| Sales Range | $100 M to 500M |
| # of Employees | 47 |
| Plant Area |
25,000
ft2
|
| Annual Production | 509,000
pieces
|
| Production Hrs. Annual | 3,060
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $47,456 | 873,669 |
kWh
|
$0.054 | |
| Electricity Demand | $35,109 | 4,272 |
kW-mo/yr
|
$8.22 | |
| Electricity Fees | $16,761 | - |
|
- | |
| Natural Gas | $8,549 | 1,594 |
MMBtu
|
$5.36 | |
| Waste Disposal Costs | |||||
| Water Disposal | $5,000 | 14,579 |
Tgal
|
$0.34 | |
| Solid Waste (haz) | $10,100 | 30,000 |
lb
|
$0.34 | |
| TOTAL YEARLY COSTS | $122,975 | ||||
| RECOMMENDED SAVINGS* | $6,376 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2313: Use batch firing with kiln "furniture" specifically designed | $3,034 | $400 | - | - |
$3,034
-
MMBtu
|
|
| 02 | 2.2442: Preheat combustion air with waste heat | $1,302 | $4,004 | - | - |
$1,302
-
MMBtu
|
|
| 03 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $533 | $276 | - | - |
$533
-
MMBtu
|
|
| 04 | 2.4221: Install compressor air intakes in coolest locations | $548 | $318 |
$343
6,316
kWh
|
$205
-
kW-mo/yr
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $258 | $200 |
$159
2,924
kWh
|
$99
-
kW-mo/yr
|
- | |
| 06 | 2.7135: Install occupancy sensors | $481 | $320 |
$481
8,864
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $220 | $321 |
$137
2,531
kWh
|
$82
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $6,376 | $5,839 |
$1,120
20,635
kWh
|
$386
-
kW-mo/yr
|
$4,869
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs