Assessment Year | 2015 |
---|---|
Principal Product | Household Furniture |
NAICS | 337127: Institutional Furniture Manufacturing |
SIC | 2521: Wood Office Furniture |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
37,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 2,550
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $51,654 | 889,200 |
kWh
|
$0.058 |
Electricity Demand | $38,626 | 4,756 |
kW-mo/yr
|
$8.12 |
Natural Gas | $50,005 | 5,760 |
MMBtu
|
$8.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,124 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,857 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,390 | $4,800 |
$14,390
243,106
kWh
|
- | - | - | |
02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $11,105 | $9,052 | - | - |
$11,105
-
MMBtu
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,465 | $25,360 |
$10,465
180,442
kWh
|
- | - | - | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,673 | $334 | - | - |
$2,673
-
MMBtu
|
- | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,166 | $4,202 | - | - |
$1,166
-
MMBtu
|
- | |
06 | 2.4322: Use or replace with energy efficient substitutes | $1,049 | $132 |
$1,049
15,767
kWh
|
- | - | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $974 | $527 |
$587
10,118
kWh
|
$387
-
kW-mo/yr
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $423 | $380 |
$255
4,396
kWh
|
$168
-
kW-mo/yr
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $288 | $100 |
$173
2,986
kWh
|
$115
-
kW-mo/yr
|
- | - | |
10 | 2.7135: Install occupancy sensors | $134 | $268 |
$134
1,935
kWh
|
- | - | - | |
11 | 4.652: Replace existing equipment with more suitable substitutes | $15,300 | $5,570 | - | - | - | $15,300 | |
12 | 2.4322: Use or replace with energy efficient substitutes | $1,070 | $391 |
$1,070
16,077
kWh
|
- | - | - | |
13 | 2.4314: Use synthetic lubricant | $654 | $1,155 |
$654
11,280
kWh
|
- | - | - | |
14 | 2.7135: Install occupancy sensors | $520 | $100 |
$313
5,405
kWh
|
$207
-
kW-mo/yr
|
- | - | |
15 | 2.7111: Reduce illumination to minimum necessary levels | $471 | $130 |
$284
4,896
kWh
|
$187
-
kW-mo/yr
|
- | - | |
16 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $310 | $125 |
$187
3,224
kWh
|
$123
-
kW-mo/yr
|
- | - | |
17 | 2.7135: Install occupancy sensors | $133 | $268 |
$133
1,935
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $61,124 | $52,894 |
$29,694
501,567
kWh
|
$1,186
-
kW-mo/yr
|
$14,944
-
MMBtu
|
$15,300 | ||
TOTAL IMPLEMENTED | $20,857 | $7,417 |
$17,778
296,836
kWh
|
$406
-
kW-mo/yr
|
$2,673
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs