ITAC Assessment: WM0069
ITAC logo
ITAC Assessment: WM0069
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Raw Forging
NAICS 332111: Iron and Steel Forging
SIC 3462: Iron and Steel Forgings
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 125,000
ft2
Annual Production 14,000,000
lb
Production Hrs. Annual 4,080
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $619,670 9,817,878
kWh
Electricity Demand $279,152 38,504
kW-mo/yr
Electricity Fees $28,231 -
Natural Gas $567,424 72,864
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $339,736 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $80,970

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4239: Eliminate or reduce compressed air usage $177,870 $500,000 $106,139
1,682,034
kWh
$71,731
-
kW-mo/yr
-
02 2.2314: Replace heat treating oven with more efficient unit $30,131 $24,450 - - $30,131
-
MMBtu
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $31,322 $95,000 $31,322
496,395
kWh
- -
04 2.1224: Replace boiler $34,455 $6,500 $(-5,939.0)
(-94,118)
kWh
- $40,394
-
MMBtu
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $19,294 $2,400 $19,294
305,766
kWh
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $27,723 - $17,029
269,869
kWh
$10,694
-
kW-mo/yr
-
07 2.4239: Eliminate or reduce compressed air usage $6,035 $855 $6,035
95,648
kWh
- -
08 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $6,282 $14,000 - - $6,282
-
MMBtu
09 2.7142: Utilize higher efficiency lamps and/or ballasts $3,822 $6,100 $2,858
45,288
kWh
$964
-
kW-mo/yr
-
10 2.7135: Install occupancy sensors $1,379 $1,500 $1,379
21,861
kWh
- -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,423 $1,600 $1,423
22,559
kWh
- -
TOTAL RECOMMENDED $339,736 $652,405 $179,540
2,845,302
kWh
$83,389
-
kW-mo/yr
$76,807
-
MMBtu
TOTAL IMPLEMENTED $80,970 $32,950 $39,181
620,923
kWh
$11,658
-
kW-mo/yr
$30,131
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs