ITAC Assessment: WM0060
ITAC logo
ITAC Assessment: WM0060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Springs, Stampings, Wire Forms
NAICS 332613: Spring Manufacturing
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 67,500
ft2
Annual Production 500
ton
Production Hrs. Annual 5,100
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,992 819,997
kWh
Electricity Demand $14,446 2,704
kW-mo/yr
Electricity Fees $14,114 -
Natural Gas $50,253 4,959
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $43,665 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,363

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.1224: Replace boiler $24,302 $20,000 - - $14,302
-
MMBtu
$10,000
02 2.4322: Use or replace with energy efficient substitutes $7,761 $2,291 $7,761
138,342
kWh
- - -
03 2.7221: Lower temperature during the winter season and vice-versa $5,355 - - - $5,355
-
MMBtu
-
04 2.1121: Use insulation in furnaces to facilitate heating / cooling $3,701 $1,218 - - $3,701
-
MMBtu
-
05 2.2135: Repair and eliminate steam leaks $1,080 $110 $882
15,714
kWh
$199
-
kW-mo/yr
- -
06 2.7135: Install occupancy sensors $786 $3,000 $507
9,043
kWh
$279
-
kW-mo/yr
- -
07 2.7447: Install vinyl strip / high speed / air curtain doors $680 $255 - - $680
-
MMBtu
-
TOTAL RECOMMENDED $43,665 $26,874 $9,150
163,099
kWh
$478
-
kW-mo/yr
$24,038
-
MMBtu
$10,000
TOTAL IMPLEMENTED $19,363 $6,874 $9,150
163,099
kWh
$478
-
kW-mo/yr
$9,736
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs