Assessment Year | 2014 |
---|---|
Principal Product | wood products |
NAICS | 321211: Hardwood Veneer and Plywood Manufacturing |
SIC | 2435: Hardwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 177 |
Plant Area |
250,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 3,536
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $251,154 | 4,223,900 |
kWh
|
$0.059 |
Electricity Demand | $122,365 | 14,433 |
kW-mo/yr
|
$8.48 |
Electricity Fees | $52,126 | - |
|
- |
Natural Gas | $502,679 | 81,651 |
MMBtu
|
$6.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,867 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,104 | $8,000 | - |
$6,104
-
kW-mo/yr
|
- | - | |
02 | 2.6212: Turn off equipment during breaks, reduce operating time | $357 | - |
$357
6,006
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,875 | $1,800 |
$501
8,430
kWh
|
$274
-
kW-mo/yr
|
- | $2,100 | |
04 | 2.6212: Turn off equipment during breaks, reduce operating time | $8,029 | - |
$8,029
135,031
kWh
|
- | - | - | |
05 | 2.7135: Install occupancy sensors | $887 | $1,575 |
$887
14,923
kWh
|
- | - | - | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $3,302 | $2,100 |
$2,225
37,425
kWh
|
$1,077
-
kW-mo/yr
|
- | - | |
07 | 3.6125: Sell combustible waste | $39,202 | $97,000 | - | - |
$39,202
-
lb
|
- | |
08 | 2.4224: Upgrade controls on compressors | $1,111 | - |
$1,111
18,689
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $61,867 | $110,475 |
$13,110
220,504
kWh
|
$7,455
-
kW-mo/yr
|
$39,202
-
lb
|
$2,100 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs