Assessment Year | 2014 |
---|---|
Principal Product | Metal heat treating and Blasting |
NAICS | 332811: Metal Heat Treating |
SIC | 3398: Metal Heat Treating |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
50,000
ft2
|
Annual Production | 8,500,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $100,328 | 1,465,344 |
kWh
|
$0.068 |
Electricity Demand | $67,483 | 5,194 |
kW-mo/yr
|
$12.99 |
Electricity Fees | $23,981 | - |
|
- |
Natural Gas | $319,946 | 55,044 |
MMBtu
|
$5.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,114 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,381 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $3,124 | $239 |
$2,293
33,470
kWh
|
$831
-
kW-mo/yr
|
|
02 | 2.4226: Use / purchase optimum sized compressor | $18,624 | $53,646 |
$13,648
199,236
kWh
|
$4,976
-
kW-mo/yr
|
|
03 | 2.2135: Repair and eliminate steam leaks | $2,471 | $270 |
$1,811
26,431
kWh
|
$660
-
kW-mo/yr
|
|
04 | 2.7135: Install occupancy sensors | $733 | $570 |
$733
10,695
kWh
|
- | |
05 | 2.3212: Optimize plant power factor | $5,162 | $24,038 | - |
$5,162
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $30,114 | $78,763 |
$18,485
269,832
kWh
|
$11,629
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $29,381 | $78,193 |
$17,752
259,137
kWh
|
$11,629
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs