Assessment Year | 1998 |
---|---|
Principal Product | Stamped Automotive Parts |
NAICS |
n/a
|
SIC | 3465: Automotive Stampings |
Sales Range | $1 M to 5M |
# of Employees | 48 |
Plant Area |
72,000
ft2
|
Annual Production | 3,500,000
lb
|
Production Hrs. Annual | 5,304
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $129,033 | 740,328 |
kWh
|
$0.17 |
Electricity Fees | $(-1,194.0) | - |
|
- |
Natural Gas | $8,356 | 2,085 |
MMBtu
|
$4.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,403 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,112 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $2,335 | $250 | - | - | - | - | $2,335 | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,860 | $1,000 |
$1,860
18,757
kWh
|
- | - | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $8,029 | $1,000 |
$8,029
80,891
kWh
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,783 | $100 |
$1,783
17,878
kWh
|
- | - | - | - | |
05 | 2.2437: Recover waste heat from equipment | $962 | $1,500 | - |
$962
-
MMBtu
|
- | - | - | |
06 | 4.611: Begin a practice of predictive / preventative maintenance | $14,994 | $5,000 | - | - |
$11,472
-
lb
|
$3,522 | - | |
07 | 4.424: Improve space comfort conditioning | $1,440 | $518 | - | - | - | $1,440 | - | |
TOTAL RECOMMENDED | $31,403 | $9,368 |
$11,672
117,526
kWh
|
$962
-
MMBtu
|
$11,472
-
lb
|
$4,962 | $2,335 | ||
TOTAL IMPLEMENTED | $13,112 | $2,618 |
$11,672
117,526
kWh
|
- | - | $1,440 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs