Assessment Year | 2018 |
---|---|
Principal Product | Pre-fabricated metal buildings |
NAICS | 332311: Prefabricated Metal Building and Component Manufacturing |
SIC | 3448: Prefabricated Metal Buildings and Components |
Sales Range | $50 M to 100M |
# of Employees | 325 |
Plant Area |
270,000
ft2
|
Annual Production | 50,000
ton
|
Production Hrs. Annual | 7,560
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $150,574 | 2,947,532 |
kWh
|
$0.051 |
Electricity Demand | $76,162 | 11,078 |
kW-mo/yr
|
$6.88 |
Electricity Fees | $1,902 | - |
|
- |
TOTAL YEARLY COSTS | $228,638 | |||
RECOMMENDED SAVINGS* | $89,050 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $57,980 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $29,830 | $29,090 |
$22,620
389,950
kWh
|
$7,210
-
kW-mo/yr
|
- | |
02 | 2.3212: Optimize plant power factor | $28,900 | $38,090 | - |
$28,900
-
kW-mo/yr
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $11,800 | $11,610 |
$10,600
183,000
kWh
|
$1,200
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,480 | $5,000 |
$8,700
150,000
kWh
|
$2,780
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,920 | $50 |
$1,910
33,000
kWh
|
$1,010
-
kW-mo/yr
|
- | |
06 | 2.4239: Eliminate or reduce compressed air usage | $2,170 | $115 |
$2,170
37,400
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,220 | $540 |
$150
2,620
kWh
|
$40
-
kW-mo/yr
|
$1,030 | |
08 | 2.6125: Keep equipment clean | $730 | $50 |
$575
9,940
kWh
|
$155
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $89,050 | $84,545 |
$46,725
805,910
kWh
|
$41,295
-
kW-mo/yr
|
$1,030 | ||
TOTAL IMPLEMENTED | $57,980 | $46,340 |
$44,555
768,510
kWh
|
$12,395
-
kW-mo/yr
|
$1,030 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs