ITAC Assessment: WM0034
ITAC logo
ITAC Assessment: WM0034
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Coating
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 36
Plant Area 60,000
ft2
Annual Production 0
units
Production Hrs. Annual 4,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,724 622,939
kWh
Electricity Demand $29,091 2,210
kW-mo/yr
Electricity Fees $2,570 -
Natural Gas $80,934 12,698
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,311 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,125

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Increase in Production Savings
01 2.4221: Install compressor air intakes in coolest locations $1,332 $276 $1,332
13,928
kWh
- - - -
02 2.8112: Combine utility meters $2,182 $5,000 - - - $2,182 -
03 2.2511: Insulate bare equipment $351 $469 - - $351
-
MMBtu
- -
04 2.7111: Reduce illumination to minimum necessary levels $367 $1,138 $114
1,520
kWh
$253
-
kW-mo/yr
- - -
05 3.1181: Eliminate a by-product $954 $2,210 - - - $954 -
06 4.424: Improve space comfort conditioning $3,125 $550 - - - - $3,125
TOTAL RECOMMENDED $8,311 $9,643 $1,446
15,448
kWh
$253
-
kW-mo/yr
$351
-
MMBtu
$3,136 $3,125
TOTAL IMPLEMENTED $3,125 $550 - - - - $3,125
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs