ITAC Assessment: MAS026
ITAC logo
ITAC Assessment: MAS026
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Aircraft fuel pumps
NAICS 336412: Aircraft Engine and Engine Parts Manufacturing
SIC 3724: Aircraft Engines and Engine Parts
Sales Range $100
M
to 500
M
# of Employees 450
Plant Area 250,000
ft2
Annual Production 350
pieces
Production Hrs. Annual 8,500
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $979,545 10,772,179
kWh
Electricity Demand $228,668 24,096
kW-mo/yr
Electricity Fees $12,349 -
Natural Gas $348,172 40,368
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $67,843 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $24,352 $59,500 - $24,352
-
MMBtu
02 2.7233: Use properly designed and sized hvac equipment $15,819 $17,200 $15,819
171,389
kWh
-
03 2.7314: Reduce ventilation air $14,331 $8,000 $5,689
61,634
kWh
$8,642
-
MMBtu
04 2.4239: Eliminate or reduce compressed air usage $10,915 $5,000 $10,915
118,260
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,426 - $2,426
26,280
kWh
-
TOTAL RECOMMENDED $67,843 $89,700 $34,849
377,563
kWh
$32,994
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs