ITAC Assessment: WM0029
ITAC logo
ITAC Assessment: WM0029
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Expanded Polystyrene (EPS)
NAICS 326140: Polystyrene Foam Product Manufacturing
SIC 3086: Plastics Foam Products
Sales Range $1
M
to 5
M
# of Employees 135
Plant Area 150,000
ft2
Annual Production 4,000
ton
Production Hrs. Annual 6,120
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $182,628 2,905,344
kWh
Electricity Demand $75,812 8,918
kW-mo/yr
Electricity Fees $16,604 -
Natural Gas $284,944 55,745
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $86,785 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,100

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $5,132 $3,066 $4,057
64,496
kWh
$1,075
-
kW-mo/yr
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $3,542 $1,240 - - $3,542
-
MMBtu
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $12,494 $2,200 $9,349
148,632
kWh
$3,145
-
kW-mo/yr
-
04 2.4314: Use synthetic lubricant $23,138 $22,800 $17,312
275,224
kWh
$5,826
-
kW-mo/yr
-
05 2.6218: Turn off equipment when not in use $9,925 $4,915 $9,925
146,673
kWh
- -
06 2.2414: Use waste heat from hot flue gases to preheat $27,541 $70,000 - - $27,541
-
MMBtu
07 2.7111: Reduce illumination to minimum necessary levels $797 $2,276 $569
9,040
kWh
$228
-
kW-mo/yr
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $149 $520 $149
1,730
kWh
- -
09 2.5123: Reduce fluid flow rates $434 $2,085 $434
6,901
kWh
- -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,633 $644 $2,872
45,655
kWh
$761
-
kW-mo/yr
-
TOTAL RECOMMENDED $86,785 $109,746 $44,667
698,351
kWh
$11,035
-
kW-mo/yr
$31,083
-
MMBtu
TOTAL IMPLEMENTED $17,100 $6,799 $12,797
192,328
kWh
$761
-
kW-mo/yr
$3,542
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs