| Assessment Year | 2013 |
|---|---|
| Principal Product | aluminum castings |
| NAICS | 331523: Nonferrous Metal Die-Casting Foundries |
| SIC | 3363: Aluminum Die-Castings |
| Sales Range | $50 M to 100M |
| # of Employees | 106 |
| Plant Area |
104,983
ft2
|
| Annual Production | 500,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $400,466 | 7,854,336 |
kWh
|
$0.051 |
| Electricity Demand | $153,036 | 17,278 |
kW-mo/yr
|
$8.86 |
| Electricity Fees | $34,506 | - |
|
- |
| Natural Gas | $51,944 | 7,928 |
MMBtu
|
$6.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,536 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,508 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $586 | $424 | - | - |
$586
-
MMBtu
|
- | |
| 02 | 2.7135: Install occupancy sensors | $1,319 | $2,730 |
$1,319
25,867
kWh
|
- | - | - | |
| 03 | 2.7229: Air condition only space necessary | $2,884 | - | - | - |
$2,884
-
MMBtu
|
- | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,454 | $1,526 | - | - |
$1,454
-
MMBtu
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $239 | $410 |
$112
1,752
kWh
|
$27
-
kW-mo/yr
|
- | $100 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,054 | $33,056 |
$18,054
354,000
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $24,536 | $38,146 |
$19,485
381,619
kWh
|
$27
-
kW-mo/yr
|
$4,924
-
MMBtu
|
$100 | ||
| TOTAL IMPLEMENTED | $19,508 | $34,582 |
$18,054
354,000
kWh
|
- |
$1,454
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs