Assessment Year | 2013 |
---|---|
Principal Product | Engraved Rotogravure cylinders |
NAICS | 323120: Support Activities for Printing |
SIC | 2796: Platemaking and Related Services |
Sales Range | $5 M to 10M |
# of Employees | 35 |
Plant Area |
43,000
ft2
|
Annual Production | 5,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
View Case Study |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $99,469 | 1,533,200 |
kWh
|
$0.065 |
Electricity Demand | $42,009 | 3,700 |
kW-mo/yr
|
$11.35 |
Electricity Fees | $22,811 | - |
|
- |
Natural Gas | $16,904 | 2,376 |
MMBtu
|
$7.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,003 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,220 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $519 | $974 |
$385
5,928
kWh
|
$135
-
kW-mo/yr
|
|
02 | 2.7135: Install occupancy sensors | $950 | $550 |
$950
14,640
kWh
|
- | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $6,156 | - |
$5,416
83,474
kWh
|
$740
-
kW-mo/yr
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $287 | - |
$212
3,273
kWh
|
$75
-
kW-mo/yr
|
|
05 | 2.4221: Install compressor air intakes in coolest locations | $264 | $276 |
$196
3,021
kWh
|
$68
-
kW-mo/yr
|
|
06 | 4.652: Replace existing equipment with more suitable substitutes | $827 | $2,009 |
$827
9,416
kWh
|
- | |
TOTAL RECOMMENDED | $9,003 | $3,809 |
$7,986
119,752
kWh
|
$1,018
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $8,220 | $2,559 |
$7,405
110,803
kWh
|
$815
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs