ITAC Assessment: WM0019
ITAC logo
ITAC Assessment: WM0019
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product gas cylindar neck rings and sleeves
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3444: Sheet Metal Work
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area 33,000
ft2
Annual Production 60,000
pieces
Production Hrs. Annual 4,080
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,744 900,536
kWh
Electricity Demand $34,573 3,045
kW-mo/yr
Electricity Fees $12,892 -
Natural Gas $50,663 8,433
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,764 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,150

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Increase in Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,135 $6,210 $947
13,811
kWh
$238
-
kW-mo/yr
- $1,950
02 2.4231: Reduce the pressure of compressed air to the minimum required $915 - $632
9,209
kWh
$283
-
kW-mo/yr
- -
03 2.7444: Close holes and openings in building such as broken windows $1,791 $1,350 - - $1,791
-
MMBtu
-
04 2.2511: Insulate bare equipment $1,985 $763 - - $1,985
-
MMBtu
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,444 $510 $5,136
74,865
kWh
$2,308
-
kW-mo/yr
- -
06 2.7495: Install replacement doors $494 $1,300 - - $494
-
MMBtu
-
TOTAL RECOMMENDED $15,764 $10,133 $6,715
97,885
kWh
$2,829
-
kW-mo/yr
$4,270
-
MMBtu
$1,950
TOTAL IMPLEMENTED $10,150 $1,860 $5,768
84,074
kWh
$2,591
-
kW-mo/yr
$1,791
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs