Assessment Year | 2013 |
---|---|
Principal Product | gas cylindar neck rings and sleeves |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
33,000
ft2
|
Annual Production | 60,000
pieces
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,744 | 900,536 |
kWh
|
$0.069 |
Electricity Demand | $34,573 | 3,045 |
kW-mo/yr
|
$11.35 |
Electricity Fees | $12,892 | - |
|
- |
Natural Gas | $50,663 | 8,433 |
MMBtu
|
$6.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,764 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,150 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,135 | $6,210 |
$947
13,811
kWh
|
$238
-
kW-mo/yr
|
- | $1,950 | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $915 | - |
$632
9,209
kWh
|
$283
-
kW-mo/yr
|
- | - | |
03 | 2.7444: Close holes and openings in building such as broken windows | $1,791 | $1,350 | - | - |
$1,791
-
MMBtu
|
- | |
04 | 2.2511: Insulate bare equipment | $1,985 | $763 | - | - |
$1,985
-
MMBtu
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,444 | $510 |
$5,136
74,865
kWh
|
$2,308
-
kW-mo/yr
|
- | - | |
06 | 2.7495: Install replacement doors | $494 | $1,300 | - | - |
$494
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $15,764 | $10,133 |
$6,715
97,885
kWh
|
$2,829
-
kW-mo/yr
|
$4,270
-
MMBtu
|
$1,950 | ||
TOTAL IMPLEMENTED | $10,150 | $1,860 |
$5,768
84,074
kWh
|
$2,591
-
kW-mo/yr
|
$1,791
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs