ITAC Assessment: WM0016
ITAC logo
ITAC Assessment: WM0016
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Cable harnesses and Integrated structures
NAICS 334419: Other Electronic Component Manufacturing
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 260
Plant Area 78,000
ft2
Annual Production 21,210
pieces
Production Hrs. Annual 8,640
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,152 1,252,200
kWh
Electricity Demand $38,422 3,384
kW-mo/yr
Electricity Fees $16,814 -
Natural Gas $12,247 1,763
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,483 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,521

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,622 $488 $2,930
44,113
kWh
$692
-
kW-mo/yr
- -
02 2.4221: Install compressor air intakes in coolest locations $652 $850 $514
7,740
kWh
$138
-
kW-mo/yr
- -
03 2.7221: Lower temperature during the winter season and vice-versa $1,517 - $1,324
19,939
kWh
$193
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $957 $270 $775
11,678
kWh
$182
-
kW-mo/yr
- -
05 2.7492: Use proper thickness of insulation on building envelope $2,769 $13,000 - - $2,769
-
MMBtu
-
06 3.5313: Increase amount of waste recovered for resale $2,004 - - - - $2,004
-
lb
07 3.5315: Lease / purchase baler; sell cardboard to recycler $962 $5,000 - - - $962
-
lb
TOTAL RECOMMENDED $12,483 $19,608 $5,543
83,470
kWh
$1,205
-
kW-mo/yr
$2,769
-
MMBtu
$2,966
-
lb
TOTAL IMPLEMENTED $3,521 - $1,324
19,939
kWh
$193
-
kW-mo/yr
- $2,004
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs