Assessment Year | 2012 |
---|---|
Principal Product | Cable harnesses and Integrated structures |
NAICS | 334419: Other Electronic Component Manufacturing |
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 260 |
Plant Area |
78,000
ft2
|
Annual Production | 21,210
pieces
|
Production Hrs. Annual | 8,640
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,152 | 1,252,200 |
kWh
|
$0.066 |
Electricity Demand | $38,422 | 3,384 |
kW-mo/yr
|
$11.35 |
Electricity Fees | $16,814 | - |
|
- |
Natural Gas | $12,247 | 1,763 |
MMBtu
|
$6.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,483 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,521 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,622 | $488 |
$2,930
44,113
kWh
|
$692
-
kW-mo/yr
|
- | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $652 | $850 |
$514
7,740
kWh
|
$138
-
kW-mo/yr
|
- | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $1,517 | - |
$1,324
19,939
kWh
|
$193
-
kW-mo/yr
|
- | - | |
04 | 2.7135: Install occupancy sensors | $957 | $270 |
$775
11,678
kWh
|
$182
-
kW-mo/yr
|
- | - | |
05 | 2.7492: Use proper thickness of insulation on building envelope | $2,769 | $13,000 | - | - |
$2,769
-
MMBtu
|
- | |
06 | 3.5313: Increase amount of waste recovered for resale | $2,004 | - | - | - | - |
$2,004
-
lb
|
|
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $962 | $5,000 | - | - | - |
$962
-
lb
|
|
TOTAL RECOMMENDED | $12,483 | $19,608 |
$5,543
83,470
kWh
|
$1,205
-
kW-mo/yr
|
$2,769
-
MMBtu
|
$2,966
-
lb
|
||
TOTAL IMPLEMENTED | $3,521 | - |
$1,324
19,939
kWh
|
$193
-
kW-mo/yr
|
- |
$2,004
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs