ITAC Assessment: WM0012
ITAC logo
ITAC Assessment: WM0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product printed circuit boards
NAICS 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing
SIC 3672: Printed Circuit Boards
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 147,000
ft2
Annual Production 775,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $238,258 3,663,000
kWh
Electricity Demand $93,442 8,490
kW-mo/yr
Electricity Fees $77,292 -
Natural Gas $25,923 5,169
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,857 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,061

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings
01 2.2437: Recover waste heat from equipment $1,304 $1,675 - $1,304
-
MMBtu
-
02 2.8114: Change rate schedules or other changes in utility service $1,345 $375 - - $1,345
-
Tgal
03 2.6212: Turn off equipment during breaks, reduce operating time $771 $100 $771
11,856
kWh
- -
04 2.7447: Install vinyl strip / high speed / air curtain doors $1,999 $5,230 $190
2,929
kWh
$1,809
-
MMBtu
-
05 2.7224: Reduce space conditioning during non-working hours $2,779 $4,500 $1,900
29,225
kWh
$879
-
MMBtu
-
06 2.7229: Air condition only space necessary $597 $975 $597
9,191
kWh
- -
07 2.7447: Install vinyl strip / high speed / air curtain doors $62 $128 $19
289
kWh
$43
-
MMBtu
-
TOTAL RECOMMENDED $8,857 $12,983 $3,477
53,490
kWh
$4,035
-
MMBtu
$1,345
-
Tgal
TOTAL IMPLEMENTED $2,061 $5,358 $209
3,218
kWh
$1,852
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs