Assessment Year | 2006 |
---|---|
Principal Product | Moldings and panels |
NAICS | 321918: Other Millwork (including Flooring) |
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
60,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,525 | 641,480 |
kWh
|
$0.040 |
Electricity Demand | $31,787 | 2,814 |
kW-mo/yr
|
$11.30 |
Natural Gas | $57,417 | 4,737 |
MMBtu
|
$12.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,275 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 4.447: Automate payroll system | $7,000 | - | - | - | $7,000 | |
02 | 4.424: Improve space comfort conditioning | $6,600 | $1,100 | - | - | $6,600 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,495 | $4,160 |
$566
13,536
kWh
|
$929
-
kW-mo/yr
|
- | |
04 | 2.4314: Use synthetic lubricant | $768 | - |
$117
2,803
kWh
|
$651
-
kW-mo/yr
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $658 | $640 |
$234
5,597
kWh
|
$424
-
kW-mo/yr
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $350 | $380 |
$132
3,170
kWh
|
$218
-
kW-mo/yr
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $212 | - |
$160
3,834
kWh
|
$52
-
kW-mo/yr
|
- | |
08 | 2.7135: Install occupancy sensors | $192 | $150 |
$192
4,950
kWh
|
- | - | |
TOTAL RECOMMENDED | $17,275 | $6,430 |
$1,401
33,890
kWh
|
$2,274
-
kW-mo/yr
|
$13,600 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs