| Assessment Year | 2006 |
|---|---|
| Principal Product | aluminum coils |
| NAICS | 331318: Other Aluminum Rolling, Drawing, and Extruding |
| SIC | 3353: Aluminum Sheet, Plate, and Foil |
| Sales Range | less than $500 k |
| # of Employees | 75 |
| Plant Area |
250,000
ft2
|
| Annual Production | 40,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $296,717 | 7,920,451 |
kWh
|
$0.037 |
| Electricity Demand | $491,352 | 62,896 |
kW-mo/yr
|
$7.81 |
| Natural Gas | $1,933,391 | 279,500 |
MMBtu
|
$6.92 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $307,891 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $42,505 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1133: Adjust burners for efficient operation | $252,960 | $360,000 | - | - |
$252,960
-
MMBtu
|
- | |
| 02 | 4.821: Pay bills on time to avoid late fees | $37,087 | - | - | - | - | $37,087 | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $9,371 | $500 | - | - |
$9,371
-
MMBtu
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,283 | - |
$2,634
79,200
kWh
|
$2,649
-
kW-mo/yr
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,055 | $1,845 |
$2,155
54,831
kWh
|
$900
-
kW-mo/yr
|
- | - | |
| 06 | 2.7261: Install timers and/or thermostats | $135 | $350 |
$135
3,435
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $307,891 | $362,695 |
$4,924
137,466
kWh
|
$3,549
-
kW-mo/yr
|
$262,331
-
MMBtu
|
$37,087 | ||
| TOTAL IMPLEMENTED | $42,505 | $350 |
$2,769
82,635
kWh
|
$2,649
-
kW-mo/yr
|
- | $37,087 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs