Assessment Year | 2005 |
---|---|
Principal Product | Conveyors |
NAICS | 333922: Conveyor and Conveying Equipment Manufacturing |
SIC | 3535: Conveyors and Conveying Equipment |
Sales Range | $10 M to 50M |
# of Employees | 145 |
Plant Area |
210,000
ft2
|
Annual Production | 8,750
pieces
|
Production Hrs. Annual | 2,625
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,023 | 1,965,960 |
kWh
|
$0.035 |
Electricity Demand | $76,586 | 7,104 |
kW-mo/yr
|
$10.78 |
Electricity Fees | $28,081 | - |
|
- |
Natural Gas | $35,845 | 3,592 |
MMBtu
|
$9.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $54,503 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,474 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.424: Improve space comfort conditioning | $21,656 | $6,750 | - | - | - | $21,656 | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,914 | $57,240 |
$7,563
204,965
kWh
|
$10,351
-
kW-mo/yr
|
- | - | - | |
03 | 2.7261: Install timers and/or thermostats | $4,904 | - | - | - |
$4,904
-
MMBtu
|
- | - | |
04 | 3.7137: Replace cloth rags with paper towels | $3,540 | - | - | - | - | - | $3,540 | |
05 | 4.426: Modify workload | $2,970 | - | - | - | - | $2,970 | - | |
06 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $1,445 | $2,000 |
$1,445
39,165
kWh
|
- | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,397 | - |
$623
16,878
kWh
|
$1,014
-
kW-mo/yr
|
- | $(-240.0) | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $677 | $1,280 |
$257
6,974
kWh
|
$420
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $54,503 | $67,270 |
$9,888
267,982
kWh
|
$11,785
-
kW-mo/yr
|
$4,904
-
MMBtu
|
$24,386 | $3,540 | ||
TOTAL IMPLEMENTED | $44,474 | $63,990 |
$7,563
204,965
kWh
|
$10,351
-
kW-mo/yr
|
$4,904
-
MMBtu
|
$21,656 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs