| Assessment Year | 2005 |
|---|---|
| Principal Product | Laminated hard wood and plywood |
| NAICS | 321999: All Other Miscellaneous Wood Product Manufacturing |
| SIC | 2499: Wood Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 128 |
| Plant Area |
348,720
ft2
|
| Annual Production | 20,000
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $167,671 | 5,591,523 |
kWh
|
$0.030 |
| Electricity Demand | $168,996 | 21,213 |
kW-mo/yr
|
$7.97 |
| Electricity Fees | $17,380 | - |
|
- |
| Natural Gas | $353,718 | 54,163 |
MMBtu
|
$6.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $67,526 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,843 | $44,480 |
$13,617
432,320
kWh
|
$7,226
-
kW-mo/yr
|
- | |
| 02 | 2.7135: Install occupancy sensors | $2,603 | $3,060 |
$2,603
82,620
kWh
|
- | - | |
| 03 | 2.7444: Close holes and openings in building such as broken windows | $14,141 | $60,000 |
$1,936
61,440
kWh
|
$1,064
-
kW-mo/yr
|
$11,141
-
MMBtu
|
|
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $13,391 | $5,500 | - | - |
$13,391
-
MMBtu
|
|
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,240 | $500 | - | - |
$2,240
-
MMBtu
|
|
| 06 | 2.2511: Insulate bare equipment | $1,787 | $400 | - | - |
$1,787
-
MMBtu
|
|
| 07 | 2.2414: Use waste heat from hot flue gases to preheat | $4,880 | $11,000 | - | - |
$4,880
-
MMBtu
|
|
| 08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,010 | - | - |
$3,010
-
kW-mo/yr
|
- | |
| 09 | 2.2437: Recover waste heat from equipment | $2,689 | - |
$1,234
39,165
kWh
|
$1,455
-
kW-mo/yr
|
- | |
| 10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,942 | $1,054 |
$1,268
40,284
kWh
|
$674
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $67,526 | $125,994 |
$20,658
655,829
kWh
|
$13,429
-
kW-mo/yr
|
$33,439
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs