Assessment Year | 2004 |
---|---|
Principal Product | Molded fiberglass parts |
NAICS | 327993: Mineral Wool Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 250 |
Plant Area |
120,000
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $167,472 | 5,096,000 |
kWh
|
$0.033 |
Electricity Demand | $136,264 | 13,120 |
kW-mo/yr
|
$10.39 |
Electricity Fees | $52,948 | - |
|
- |
Natural Gas | $370,959 | 53,189 |
MMBtu
|
$6.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,617 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,164 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,449 | $18,810 | n/a |
$6,777
195,293
kWh
|
$3,672
-
kW-mo/yr
|
- |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $7,950 | $10,000 | - | - |
$7,950
-
MMBtu
|
|
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,804 | $500 | - | - |
$3,804
-
MMBtu
|
|
04 | 2.4239: Eliminate or reduce compressed air usage | $6,164 | $830 |
$914
26,334
kWh
|
$5,250
-
kW-mo/yr
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,971 | $2,186 |
$1,842
53,083
kWh
|
$1,129
-
kW-mo/yr
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,886 | - |
$1,196
34,465
kWh
|
$690
-
kW-mo/yr
|
- | |
07 | 2.2511: Insulate bare equipment | $393 | $40 | - | - |
$393
-
MMBtu
|
|
TOTAL RECOMMENDED | $33,617 | $32,366 |
$10,729
309,175
kWh
|
$10,741
-
kW-mo/yr
|
$12,147
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,164 | $830 |
$914
26,334
kWh
|
$5,250
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs