ITAC Assessment: WI0477
ITAC logo
ITAC Assessment: WI0477
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Stainless Steel Punps
NAICS 333911: Pump and Pumping Equipment Manufacturing
SIC 3561: Pumps and Pumping Equipment
Sales Range $10
M
to 50
M
# of Employees 84
Plant Area 100,000
ft2
Annual Production 5,500
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,049 926,810
kWh
Electricity Demand $32,039 3,134
kW-mo/yr
Electricity Fees $4,202 -
Natural Gas $11,150 1,350
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,292 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $938

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $10,743 - - $10,743
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,524 $855 $2,841
51,940
kWh
$1,683
-
kW-mo/yr
-
03 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation $2,765 $605 $1,517
27,734
kWh
$1,248
-
kW-mo/yr
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,817 $433 $1,817
33,232
kWh
- -
05 2.7261: Install timers and/or thermostats $923 - - - $923
-
MMBtu
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $938 - $508
9,284
kWh
$430
-
kW-mo/yr
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $582 - $365
6,684
kWh
$217
-
kW-mo/yr
-
TOTAL RECOMMENDED $22,292 $1,893 $7,048
128,874
kWh
$14,321
-
kW-mo/yr
$923
-
MMBtu
TOTAL IMPLEMENTED $938 - $508
9,284
kWh
$430
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs