Assessment Year | 2004 |
---|---|
Principal Product | Control Valves |
NAICS | 334512: Automatic Environmental Control Manufacturing for Residential, Commercial, and Appliance Use |
SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
88,000
ft2
|
Annual Production | 450,000
pieces
|
Production Hrs. Annual | 5,400
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $68,523 | 2,102,920 |
kWh
|
$0.033 |
Electricity Demand | $53,559 | 5,085 |
kW-mo/yr
|
$10.53 |
Electricity Fees | $22,125 | - |
|
- |
Natural Gas | $22,492 | 2,878 |
MMBtu
|
$7.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,523 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,068 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,303 | $15,076 |
$4,248
124,362
kWh
|
$3,055
-
kW-mo/yr
|
- | |
02 | 4.652: Replace existing equipment with more suitable substitutes | $5,108 | $59,785 | - | - |
$5,108
-
MMBtu
|
|
03 | 2.2437: Recover waste heat from equipment | $1,338 | $800 |
$1,338
19,532
kWh
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $455 | - |
$267
7,734
kWh
|
$188
-
kW-mo/yr
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $319 | $640 |
$175
5,196
kWh
|
$144
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $14,523 | $76,301 |
$6,028
156,824
kWh
|
$3,387
-
kW-mo/yr
|
$5,108
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,068 | $76,301 |
$5,761
149,090
kWh
|
$3,199
-
kW-mo/yr
|
$5,108
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs