Assessment Year | 1994 |
---|---|
Principal Product | Gerotors |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 450 |
Plant Area |
130,000
ft2
|
Annual Production | 17,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,205,430 | 14,800,411 |
kWh
|
$0.081 |
Natural Gas | $110,014 | 19,241 |
MMBtu
|
$5.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $136,522 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $42,534 | $50,000 |
$96,637
1,187,573
kWh
|
$(-54,103.0)
-
MMBtu
|
- | |
02 | 2.2515: Use optimum thickness insulation | $22,500 | $4,500 |
$22,500
277,843
kWh
|
- | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $35,300 | $70,000 |
$50,100
615,475
kWh
|
$(-14,800.0)
-
MMBtu
|
- | |
04 | 2.3212: Optimize plant power factor | $9,485 | $9,080 |
$9,485
-
kWh
|
- | - | |
05 | 3.4155: Meter waste water | $18,700 | $1,350 | - | - |
$18,700
-
Tgal
|
|
06 | 2.5123: Reduce fluid flow rates | $1,088 | $1,010 |
$1,088
13,482
kWh
|
- | - | |
07 | 2.2437: Recover waste heat from equipment | $6,915 | $30,000 | - |
$6,915
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $136,522 | $165,940 |
$179,810
2,094,373
kWh
|
$(-61,988.0)
-
MMBtu
|
$18,700
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs