ITAC Assessment: ME0137
ITAC logo
ITAC Assessment: ME0137
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Gerotors
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 450
Plant Area 130,000
ft2
Annual Production 17,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,205,430 14,800,411
kWh
Natural Gas $110,014 19,241
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $136,522 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $42,534 $50,000 $96,637
1,187,573
kWh
$(-54,103.0)
-
MMBtu
-
02 2.2515: Use optimum thickness insulation $22,500 $4,500 $22,500
277,843
kWh
- -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $35,300 $70,000 $50,100
615,475
kWh
$(-14,800.0)
-
MMBtu
-
04 2.3212: Optimize plant power factor $9,485 $9,080 $9,485
-
kWh
- -
05 3.4155: Meter waste water $18,700 $1,350 - - $18,700
-
Tgal
06 2.5123: Reduce fluid flow rates $1,088 $1,010 $1,088
13,482
kWh
- -
07 2.2437: Recover waste heat from equipment $6,915 $30,000 - $6,915
-
MMBtu
-
TOTAL RECOMMENDED $136,522 $165,940 $179,810
2,094,373
kWh
$(-61,988.0)
-
MMBtu
$18,700
-
Tgal
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs