| Assessment Year | 2004 |
|---|---|
| Principal Product | Corrugated Containers |
| NAICS | 321920: Wood Container and Pallet Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 350 |
| Plant Area |
270,000
ft2
|
| Annual Production | 1,800,000
thousand feet
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $269,615 | 9,270,200 |
kWh
|
$0.029 |
| Electricity Demand | $260,686 | 26,327 |
kW-mo/yr
|
$9.90 |
| Electricity Fees | $30,590 | - |
|
- |
| Natural Gas | $587,442 | 108,787 |
MMBtu
|
$5.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $225,486 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $66,949 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $124,013 | $650,000 |
$107,700
3,000,000
kWh
|
$125,400
-
kW-mo/yr
|
$(-109,087.0)
-
MMBtu
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $52,024 | $103,390 |
$33,193
1,081,224
kWh
|
$18,831
-
kW-mo/yr
|
- | - | |
| 03 | 2.7135: Install occupancy sensors | $673 | $150 |
$673
21,954
kWh
|
- | - | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $16,655 | $13,500 | - | - |
$16,655
-
MMBtu
|
- | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $9,209 | $16,500 | - | - |
$9,209
-
MMBtu
|
- | |
| 06 | 3.4114: Replace city water with recycled water via cooling tower | $14,113 | $10,500 |
$(-1,237.0)
(-40,284)
kWh
|
$(-702.0)
-
kW-mo/yr
|
- |
$16,052
-
Tgal
|
|
| 07 | 2.4221: Install compressor air intakes in coolest locations | $5,043 | $1,280 |
$3,094
100,773
kWh
|
$1,949
-
kW-mo/yr
|
- | - | |
| 08 | 2.7221: Lower temperature during the winter season and vice-versa | $2,932 | $360 | - | - |
$2,932
-
MMBtu
|
- | |
| 09 | 2.4133: Use most efficient type of electric motors | $824 | $1,600 |
$506
16,460
kWh
|
$318
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $225,486 | $797,280 |
$143,929
4,180,127
kWh
|
$145,796
-
kW-mo/yr
|
$(-80,291.0)
-
MMBtu
|
$16,052
-
Tgal
|
||
| TOTAL IMPLEMENTED | $66,949 | $121,320 |
$36,960
1,203,951
kWh
|
$20,780
-
kW-mo/yr
|
$9,209
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs