Assessment Year | 2004 |
---|---|
Principal Product | Blinds |
NAICS | 337920: Blind and Shade Manufacturing |
SIC | 2591: Drapery Hardware and Window Blinds and Shades |
Sales Range | $50 M to 100M |
# of Employees | 500 |
Plant Area |
250,000
ft2
|
Annual Production | 420,000,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $554,870 | 15,684,787 |
kWh
|
$0.035 |
Electricity Demand | $286,959 | 30,181 |
kW-mo/yr
|
$9.51 |
Electricity Fees | $53,929 | - |
|
- |
Natural Gas | $304,940 | 41,853 |
MMBtu
|
$7.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $148,891 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.4114: Replace city water with recycled water via cooling tower | $75,927 | $18,500 |
$(-4,854.0)
(-930,996)
kWh
|
- | - |
$80,781
-
Tgal
|
|
02 | 2.1221: Replace obsolete burners with more efficient ones | $17,690 | $17,690 | - | - |
$17,690
-
MMBtu
|
- | |
03 | 2.2437: Recover waste heat from equipment | $15,360 | $2,000 | - | - |
$15,360
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,859 | $29,148 |
$10,002
268,162
kWh
|
$3,857
-
kW-mo/yr
|
- | - | |
05 | 2.4224: Upgrade controls on compressors | $11,920 | $12,595 |
$11,920
319,586
kWh
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $7,605 | $840 |
$5,231
140,245
kWh
|
$2,374
-
kW-mo/yr
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,530 | $15,200 |
$6,530
175,104
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $148,891 | $95,973 |
$28,829
(-27,899)
kWh
|
$6,231
-
kW-mo/yr
|
$33,050
-
MMBtu
|
$80,781
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs