Assessment Year | 1997 |
---|---|
Principal Product | yachts |
NAICS |
n/a
|
SIC | 3732: Boat Building and Repairing |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
66,000
ft2
|
Annual Production | 60
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $44,331 | 582,356 |
kWh
|
$0.076 |
Electricity Demand | $16,156 | 1,889 |
kW-mo/yr
|
$8.55 |
Electricity Fees | $1,436 | - |
|
- |
Fuel Oil #2 | $16,781 | 2,661 |
MMBtu
|
$6.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,680 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,968 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,383 | $7,504 |
$2,921
41,032
kWh
|
$3,540
-
kW-mo/yr
|
$(-1,078.0)
-
MMBtu
|
- | - | |
02 | 2.2515: Use optimum thickness insulation | $790 | $960 | - | - |
$790
-
MMBtu
|
- | - | |
03 | 2.8121: Apply for tax-free status for energy purchases | $756 | - | - | - | - | $756 | - | |
04 | 2.2515: Use optimum thickness insulation | $515 | $588 |
$515
4,689
kWh
|
- | - | - | - | |
05 | 4.821: Pay bills on time to avoid late fees | $512 | - | - | - | - | $512 | - | |
06 | 2.2515: Use optimum thickness insulation | $408 | $75 |
$408
5,862
kWh
|
- | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $359 | $100 |
$359
5,275
kWh
|
- | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $217 | $185 |
$217
3,224
kWh
|
- | - | - | - | |
09 | 3.5313: Increase amount of waste recovered for resale | $1,200 | - | - | - | - | - | $1,200 | |
10 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $540 | $1,188 | - | - | - | - | $540 | |
TOTAL RECOMMENDED | $10,680 | $10,600 |
$4,420
60,082
kWh
|
$3,540
-
kW-mo/yr
|
$(-288.0)
-
MMBtu
|
$1,268 | $1,740 | ||
TOTAL IMPLEMENTED | $8,968 | $10,600 |
$4,420
60,082
kWh
|
$3,540
-
kW-mo/yr
|
$(-288.0)
-
MMBtu
|
$756 | $540 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs