Assessment Year | 2003 |
---|---|
Principal Product | Medical, Commercial, Lenticular signing |
NAICS | 326113: Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing |
SIC | 3081: Unsupported Plastics Film and Sheet |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
73,000
ft2
|
Annual Production | 48,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $371,293 | 13,284,000 |
kWh
|
$0.028 |
Electricity Demand | $126,690 | 26,844 |
kW-mo/yr
|
$4.72 |
Electricity Fees | $151,620 | - |
|
- |
Natural Gas | $17,289 | 2,310 |
MMBtu
|
$7.48 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $51,229 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $20,554 | $25,000 |
$15,949
544,320
kWh
|
$4,605
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,687 | $27,555 |
$10,070
343,686
kWh
|
$2,617
-
kW-mo/yr
|
|
03 | 2.4224: Upgrade controls on compressors | $8,675 | $2,014 |
$8,675
296,087
kWh
|
- | |
04 | 4.422: Utilize outside contracting | $5,139 | $1,240 |
$4,293
146,507
kWh
|
$846
-
kW-mo/yr
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,517 | $1,605 |
$2,040
69,626
kWh
|
$477
-
kW-mo/yr
|
|
06 | 2.3132: Recharge batteries on during off-peak demand periods | $1,657 | $1,000 | - |
$1,657
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $51,229 | $58,414 |
$41,027
1,400,226
kWh
|
$10,202
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs