ITAC Assessment: WI0445
ITAC logo
ITAC Assessment: WI0445
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product machine Spindles/Slides
NAICS 332710: Machine Shops
SIC 3541: Machine Tools, Metal Cutting Types
Sales Range $10
M
to 50
M
# of Employees 82
Plant Area 88,000
ft2
Annual Production 4,000
pieces
Production Hrs. Annual 6,250
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,957 1,796,100
kWh
Electricity Demand $52,355 4,995
kW-mo/yr
Electricity Fees $12,803 -
Natural Gas $12,492 2,017
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,656 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,147

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 3.7137: Replace cloth rags with paper towels $4,725 - - - - - $4,725 -
02 3.6112: Use filter and drying oven to reduce sludge volume $3,022 $10,000 n/a - - $(-418.0)
-
MMBtu
$3,440
-
gal
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,188 $4,400 $2,188
62,005
kWh
- - - - -
04 3.2123: Convert to high volume low pressure (hvlp) paint guns $1,188 $1,000 - - - - - $1,188
05 2.4224: Upgrade controls on compressors $1,111 $2,500 $1,111
31,472
kWh
- - - - -
06 2.4221: Install compressor air intakes in coolest locations $422 $640 $296
8,393
kWh
$126
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $12,656 $18,540 $3,595
101,870
kWh
$126
-
kW-mo/yr
$(-418.0)
-
MMBtu
$3,440
-
gal
$4,725 $1,188
TOTAL IMPLEMENTED $5,147 $640 $296
8,393
kWh
$126
-
kW-mo/yr
- - $4,725 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs