| Assessment Year | 2002 |
|---|---|
| Principal Product | Seating |
| NAICS |
n/a
|
| SIC | 2531: Public Building and Related Furniture |
| Sales Range | $10 M to 50M |
| # of Employees | 85 |
| Plant Area |
40,000
ft2
|
| Annual Production | 30,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $25,304 | 744,800 |
kWh
|
$0.034 |
| Electricity Demand | $25,194 | 2,752 |
kW-mo/yr
|
$9.15 |
| Electricity Fees | $5,174 | - |
|
- |
| Natural Gas | $16,472 | 2,550 |
MMBtu
|
$6.46 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,914 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,483 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.4114: Replace city water with recycled water via cooling tower | $7,907 | $13,000 |
$(-1,022.0)
(-14,920)
kWh
|
- | - |
$8,929
-
Tgal
|
|
| 02 | 2.7261: Install timers and/or thermostats | $1,742 | $600 | - | - |
$1,742
-
MMBtu
|
- | |
| 03 | 2.7135: Install occupancy sensors | $1,532 | $5,000 |
$799
22,380
kWh
|
$733
-
kW-mo/yr
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $623 | $300 |
$308
8,640
kWh
|
$315
-
kW-mo/yr
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $205 | - |
$107
3,008
kWh
|
$98
-
kW-mo/yr
|
- | - | |
| 06 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $369 | $525 |
$369
10,340
kWh
|
- | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $282 | $640 |
$167
4,676
kWh
|
$115
-
kW-mo/yr
|
- | - | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $254 | $90 |
$150
1,460
kWh
|
$104
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $12,914 | $20,155 |
$878
35,584
kWh
|
$1,365
-
kW-mo/yr
|
$1,742
-
MMBtu
|
$8,929
-
Tgal
|
||
| TOTAL IMPLEMENTED | $2,483 | $1,330 |
$424
9,144
kWh
|
$317
-
kW-mo/yr
|
$1,742
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs