ITAC Assessment: WI0431
ITAC logo
ITAC Assessment: WI0431
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Seating
NAICS
n/a
SIC 2531: Public Building and Related Furniture
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 40,000
ft2
Annual Production 30,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,304 744,800
kWh
Electricity Demand $25,194 2,752
kW-mo/yr
Electricity Fees $5,174 -
Natural Gas $16,472 2,550
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,914 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,483

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 3.4114: Replace city water with recycled water via cooling tower $7,907 $13,000 $(-1,022.0)
(-14,920)
kWh
- - $8,929
-
Tgal
02 2.7261: Install timers and/or thermostats $1,742 $600 - - $1,742
-
MMBtu
-
03 2.7135: Install occupancy sensors $1,532 $5,000 $799
22,380
kWh
$733
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $623 $300 $308
8,640
kWh
$315
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $205 - $107
3,008
kWh
$98
-
kW-mo/yr
- -
06 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $369 $525 $369
10,340
kWh
- - -
07 2.4221: Install compressor air intakes in coolest locations $282 $640 $167
4,676
kWh
$115
-
kW-mo/yr
- -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $254 $90 $150
1,460
kWh
$104
-
kW-mo/yr
- -
TOTAL RECOMMENDED $12,914 $20,155 $878
35,584
kWh
$1,365
-
kW-mo/yr
$1,742
-
MMBtu
$8,929
-
Tgal
TOTAL IMPLEMENTED $2,483 $1,330 $424
9,144
kWh
$317
-
kW-mo/yr
$1,742
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs